Summer Mill And Overlay Project Is A Wrap

Current News Posted on September 15, 2025

The City completed its in-house mill and overlay project over the summer, resurfacing 2.59 miles of roadway. Paving occurred from July 14 through July 30. Despite some weather delays, crews laid 4,490 tons of asphalt over 10 workdays. This work helps extend pavement life and improve safety. 